Qademah Fault Project
Sept. – Oct.
2014
Objective
Two
data sets are collected, the first is active-source data set, and the second is
a passive data set.
Geophones and cables are planted on Sept. 25, 2014. We used 12 lines
each line has 24 receivers. The inline interval is 5 m and the crossline interval is 10 m.
Acquisition Team
Sherif, Kai, Mrinal, Bowen, and Ahmed
Figure 1: Study Area
Acquisition Layout
We
used 288 receiver arranged in 12 parallel lines, each line has 24 receiver.
Inline offset is 5 m and crossline offset is 10 m
(see Figure 2).
One shot is fired at each receiver location
(see Figure 3).
We use the 40 kgm
weight drop as seismic source (Figure 4), with 8 to 15 stacks at each shot
location.
Figure 2: Shot/Receiver layout. Small black dots are
the receiver/source location.
Figure 3: Shooting at each receiver location
Data Sets